Why you need a PEC licence

  • Legal requirement to bid/execute public works and most private engineering projects in Pakistan. Pakistan Engineering Council – PEC
  • Apply and track everything online via the PEC CO Portal.

Constructor / Operator License Categories (C-6 → C-A & O-6 → O-A)

  • What each category means (single-project limit, engineers/PCPs, typical bank balance):

    PCPs = Professional Credit Points (points awarded per employed engineer; PEC publishes the PCP requirement per category).

    • C-6 (entry)
      • Project limit: PKR 25 million
      • Engineers / PCPs: ≥1 Registered Engineer or 5 PCPs
      • Indicative bank balance: ~PKR 1.5 million
      • SECP company: Not mandatory
    • C-5
      • Project limit: PKR 65 million
      • Engineers / PCPs: ≥1 RE or 5 PCPs
      • Indicative bank balance: ~PKR 3 million
    • C-4
      • Project limit: PKR 200 million
      • Engineers / PCPs: ~15 PCPs (often ≈3 fresh engineers)
      • Indicative bank balance: ~PKR 6 million
    • C-3
      • Project limit: PKR 500 million
      • Engineers / PCPs: ~20 PCPs
      • Indicative bank balance: ~PKR 30 million
    • C-2
      • Project limit: PKR 1,000 million (1 billion)
      • Engineers / PCPs: ~35 PCPs (incl. ≥1 Professional Engineer + ≥1 Trainee Engineer)
      • Indicative bank balance: ~PKR 50 million
    • C-1
      • Project limit: PKR 2,500 million (2.5 billion)
      • Engineers / PCPs: ~90 PCPs
      • Indicative bank balance: ~PKR 80 million
    • C-B
      • Project limit: PKR 4,000 million (4.0 billion)
      • Engineers / PCPs: ~120 PCPs
      • Indicative bank balance: ~PKR 100 million
    • C-A (No Limit)
      • Project limit: No upper limit
      • Engineers / PCPs: ~200 PCPs
      • Indicative bank balance: ~PKR 150 million

    Operator (O-6 → O-A) follow the same idea but for operation/maintenance works; PCPs mirror Constructors at each level. PEC sets Standard vs. Provisional PCPs (e.g., C-1 Standard 90 PCPs; C-1 Provisional 45).

PEC Contractor Categories

PEC Operator Categories

Note: From O-6 to O-3, employment of R.E as Trainee Engineer is not required/eligible.

Note: Exact PCP counts are published by PEC; “indicative bank balances” shown above reflect common practice from the sources you provided, while official PCP tables come from PEC’s portal. Always confirm the precise current number on the CO Portal PCPs page and fee calculator before filing.

Your Quick Questions and Answers

  • Pakistani Constructor/Operator Firms: PEC posts fee tables (new/renewal) and category-wise calculators on its site. Use Fee and PCPs calculators inside the CO Portal for the latest payable amount.
  • Consulting Engineering Firms (local): Annual registration/renewal fee by ownership type (PKR):
    • Individual/Sole-proprietor: 10,000
    • Partnership: 20,000
    • Private Ltd: 30,000
    • Public Ltd: 50,000

Foreign constructors/operators: fee pages and categories (FC-A/FO-A, etc.) available on PEC’s site

  • Who: Firms providing design, supervision, and consulting (not executing works).
  • Registration: Annual by ownership type (fees above).
  • Core requirements typically include:
    • Valid engineers (RE/PE) employed and listed with PEC
    • Company/firm docs (CNICs, NTN, SECP where applicable)
    • Proof of experience/project references as relevant to codes
    • Payment voucher and application package
      (See PEC forms/downloads section.)
  • Company identity: CNICs, NTN, business registration; SECP documents if a company.
  • Bank proof: Closing bank balance meeting your target category; bank maintenance certificate.
  • Engineering staff: Employed REs/PEs matching PCP requirement; trainee engineers mandatory for higher tiers as per PEC guidelines.
  • Work orders/performance certificates for up-gradation (where applicable).
  • Signed forms & fee vouchers (download from PEC’s site).
  •  

Step 1 — Pick category & codes: Use PCPs Calculator and Codes Detail in CO Portal.

Step 2 — Create CO Portal account (Chrome recommended).

Step 3 — Upload docs & pay fee (PEC bank details and vouchers available on site).

  • Starting out, small private works? C-6 / C-5 (no SECP needed for C-6).
  • Mid-size public bids? C-4 / C-3 (confirm PCPs & balances).
  • Large public portfolios? C-2 / C-1.
  • Mega / unlimited? C-A (No Limit) with 200 PCPs.

 We help you choose the right category & codes, prepare bank/PCP compliance, and structure engineer staffing so you pass PEC checks the first time.
Need up-gradation (e.g., C-5 → C-4 → C-3)? We’ll map your completed works + PCPs to the correct tier and file clean.
Call / WhatsApp: +92-316-422-7546
Email / Site: gillanigrp.com

PCP numbers and fee schedules are published/maintained by PEC and can change via Governing Body decisions; always verify your final PCP count and payable fee in the CO Portal calculators at filing time.